Written by the GXI team | Last updated: 24 November 2026 | Reviewed by: GXI Project Delivery
TL;DR:
Six levers cut fit out costs without cutting quality:
(1) fix the brief and cost plan before design
(2) reuse sound existing elements
(3) size the layout to real attendance
(4) pick design and build with early contractor input
(5) spend on high-impact zones and lifetime efficiency
(6) protect the programme and the lease
UK all-in fit out costs typically run £111 to £218+ per sq ft, and a 5% to 15% contingency should sit as its own budget line.
Fit out budgets rarely fail because of one big mistake. They drift through a dozen small decisions made too late: a layout drawn before anyone priced it, partitions built where open space would do, finishes chosen from a catalogue instead of a budget. For any business weighing a commercial fit out in Stevenage, most of those decisions can be controlled early, and controlling them does not mean accepting a poorer result.
This guide answers a question we hear often: are there ways to reduce office fit out costs without compromising quality? There are, and six of them account for most of the realistic savings. Each one below includes the numbers, the trade-offs and what to ask your contractor.
What Fit Out Costs Look Like in Stevenage Right Now
Stevenage is a science and engineering town. Life sciences, aerospace and defence, and technology drive office demand, and STEM roles make up roughly 51% of the town's 54,000 jobs, according to Stevenage Borough Council papers on the GSK site. The main occupier hubs are the Gunnels Wood Road corridor, Arlington Business Park off Whittle Way, the 25-acre Stevenage Bioscience Catalyst campus, the 42,000 sq ft Business and Technology Centre on Bessemer Drive and the regenerating town centre around Town Square and the planned Station Gateway.
Budgets for an office fit out in Stevenage generally sit well below London levels. The Stevenage employment baseline study records office vacancy of roughly 13%, above the 8% to 10% usually seen as normal, which gives tenants room to negotiate landlord contributions and rent-free periods that offset fit out spend.

|
Benchmark (per sq ft) |
Range |
Source |
|
London, all-in (low to high) |
£148 to £359 |
|
|
Manchester, all-in (low to high) |
£128 to £310 |
|
|
Hertfordshire Cat A |
£40 to £80 |
|
|
Hertfordshire Cat B |
£55 to £125+ |
|
|
Stevenage construction only, standard scope |
£70 to £120 |
Treat the Hertfordshire and Stevenage figures as indicative. They come from contractor-published guides, not audited cost data, so use them to sense-check quotes rather than to set a fixed budget.
A Worked Example: What a 5,000 sq ft Budget Looks Like
Numbers make the six levers concrete. Using Our all-in component ranges, a 5,000 sq ft project would break down as follows. These are illustrative UK figures, not a quote.
|
Component |
Per sq ft |
5,000 sq ft total |
|
Construction |
£70 to £120 |
£350,000 to £600,000 |
|
Furniture |
£20 to £60 |
£100,000 to £300,000 |
|
AV and IT |
£5 to £15 |
£25,000 to £75,000 |
|
Dilapidations and compliance |
£15 to £20 |
£75,000 to £100,000 |
|
Security |
£1 to £3 |
£5,000 to £15,000 |
|
All-in total |
£111 to £218 |
£555,000 to £1,090,000 |
The gap between the low and high columns is the cost of specification and scope decisions. That is why the six ways below focus on decisions, not on squeezing contractor margins. Reusing furniture alone moves the furniture line, a leaner layout trims construction, and an early cost plan keeps the total from drifting towards the top of the range.
1. Fix the Brief and the Cost Plan Before You Design
The most expensive changes are the ones made after drawings are issued. A vague brief causes re-design, rework across mechanical, electrical and construction packages, and programme slippage, as MGL Projects notes. Designing first and fixing the budget later through value engineering usually strips out the features you cared about most.
Know where the money goes before you start. A typical all-in project like this:
- Construction: £70 to £120 per sq ft
- Furniture: £20 to £60 per sq ft
- AV and IT: £5 to £15 per sq ft
- Dilapidations and compliance: £15 to £20 per sq ft
- Security: £1 to £3 per sq ft
Mechanical and electrical services typically take 35% to 45% of the budget, as covered in GXI's guide to office fit out cost factors, and professional fees add 10% to 15%, according to Area.
Set contingency as a separate line and let it shrink as design firms up. Ethos Engineering suggests 8% to 15% at concept stage, 5% to 10% once layouts are fixed, and 2% to 5% at technical design. Contingency is for genuine unknowns, not upgrades.
When you brief office fit out companies in Stevenage, ask for a cost plan at concept stage, not after tender, and ask what each design decision adds or saves per sq ft.

2. Reuse What Is Sound Instead of Replacing Everything
Reuse is usually the largest single saving. Industry guidance suggests that retaining sound partitions, ceilings and mechanical and electrical services can cut overall costs by 25% to 40%, as set out by Office Refurbishment London. The same guide reports savings of up to 42% on furniture, fixtures and fittings, and JLL's circular fit out guide explains why retaining an outgoing tenant's fit out can save even more.
Reuse is not a straight 1:1 price drop. Dismantling, cleaning, altering ceiling grids and repositioning lights all take labour, so compare the cost of adapting an asset with demolition plus replacement. A well scoped office refurbishment in Stevenage starts with a survey of what can stay.
|
Element |
Keep when |
Replace when |
|
Workstations and storage |
Frames are sound and finishes can be refurbished |
Layout no longer fits or ergonomics fail |
|
Partitions and glazing |
Positions suit the new plan |
Acoustic or fire performance is below standard |
|
Ceilings and lighting |
Grid and fittings are in good condition |
You are converting to LED or changing layout |
|
Flooring |
Tiles can be cleaned or patched |
Wear, trip hazards or a new brand scheme |
Watch the Cat A and Cat B hand-off. Many costs arise when an incoming tenant rips out brand new Cat A ceilings and lighting to fit a bespoke Cat B design. Agree the two scopes early so nothing is built twice.
3. Size the Layout to How People Actually Work
Every partition has a price. Walls and doors are labour and material heavy, and they force changes to lighting, HVAC and sprinklers, as Zentura Workspace points out. Modular meeting pods, phone booths and acoustic furniture can create privacy without heavy construction.
Hybrid working changes how many desks you need. Hubble gives these planning ratios:
|
Office attendance |
Desks per employee |
|
2 days a week |
0.45 to 0.60 |
|
3 days a week (most common) |
0.60 to 0.75 |
|
4 days a week |
0.80 to 0.90 |
|
5 days a week |
1.0 |
Average UK offices now provide about 56 desks per 100 employees, down from 79 in 2022, according to Tileyard North. Size to peak-day attendance plus a 10% buffer rather than to headcount, as Hagerstone advises, and convert freed space into collaboration zones and focus rooms that earn their keep.
Good office refurbishment services in Stevenage should include space planning that tests attendance data before a single wall is drawn.

4. Choose Design and Build and Bring the Contractor in Early
Design and build puts design and construction under one contract. Cost certainty arrives sooner, there are fewer overlapping consultant fees, and running design and build in parallel can shorten the programme by 30% to 40%, according to WRK and RAP Interiors. It also avoids tender shock, where bids land over budget and features are stripped out afterwards.
It is not always cheapest. Hog Group notes that traditional procurement can suit listed buildings, laboratories and other technically complex spaces, and that a shifting brief makes fixed-price design and build expensive. Given Stevenage's lab and R&D occupiers, match the route to the building and the brief.
Early contractor involvement attacks cost directly. It replaces risk pricing with real pricing, flags clashes such as low ceiling heights on paper, and checks live lead times before you specify something that arrives late. Value engineering then trims waste without cutting performance:
- Swap solid stone worktops for high-grade laminate
- Standardise joinery modules across the floorplate
- Rationalise dense lighting layouts to fewer, better fittings
- Balance upfront savings against wear and maintenance
Niche Projects, an Australian specialist, cites savings of 10% to 30% from starting value engineering early. Treat that as an indicative range.
Appoint fit out contractors in Stevenage at concept stage, not after the design is frozen, so buildability and price shape the design.

5. Spend Where It Shows and Save on Lifetime Costs
Not every square foot needs the same finish. Put budget into reception and main meeting rooms, where clients and staff judge your business, and keep back-of-house areas simpler. Mid-range options such as commercial-grade carpet tiles and high-pressure laminate give longevity without the premium, as Truline describes.
Lighting is where upfront spend pays back fastest. Renewable Energy Hub estimates about £60 per fixture:
|
Office size |
Approx. fixtures |
LED upgrade cost |
|
1,000 sq ft |
20 |
£1,200 to £1,800 |
|
5,000 sq ft |
100 |
£6,000 to £9,000 |
|
10,000 sq ft |
200 |
£12,000 to £18,000 |
LEDs cut lighting energy use by 50% to 80%, and Bionic puts typical payback at one to three years.
Efficiency also protects the lease. Privately rented commercial offices must currently hold an EPC rating of E or better. The June 2026 update reported by RICS cancelled the proposed EPC C milestone for 2027 and points to EPC B from 2031 for private rented buildings over 1,000 square metres, subject to secondary legislation.
Some items should never be cut: ergonomic seating, electrical and data cabling, and compliance work. Cutting them usually costs more later.
Specialist office refurbishment companies in Stevenage can model lighting, controls and glazing upgrades against payback so the efficient option is priced beside the cheap one.
6. Protect the Programme and the Lease
Time is a cost line. A typical 5,000 to 10,000 sq ft fit out runs 5 to 8 months from briefing to handover, with 8 to 16 weeks on site, according to Hog Group and Eden Build. Delay brings extended site preliminaries, plant hire, storage for delivered furniture and, if your old lease expires, double rent. One contractor guide from Constructing Culture suggests burn rates of about 0.25% to 0.5% of contract value per week, though that is an indicative figure.
Order long-lead items such as acoustic glazing and custom joinery early, and secure the licence for alterations before you commit to dates. If you must stay in the building, remember occupied works can add 30% to 50% to site time, per Hog Group. GXI's guide to phased refurbishment budgeting explains when phasing is worth it: it spreads cash flow and avoids relocation costs, but it carries a construction premium.
Plan the exit as well. Dilapidations typically run £8 to £45 per sq ft, according to Renova UK, and The Levy Group reports that a landlord's first schedule is frequently reduced by 30% to 60% on review. Negotiate rent-free periods and contributions at lease stage, when vacancy is on your side.
Ask commercial fit out companies in Stevenage for a programme that shows long-lead orders, landlord approvals and handover dates, not just a completion week.

Questions to Ask Before You Sign Any Fit Out Contract
Use these to test whether a quote protects both your budget and your quality:
- Which items in this price are provisional sums, and what could they become?
- What has been assumed about the existing ceiling, services and floor condition?
- Which elements have you recommended we retain, and what saving does that represent?
- Where is contingency held, and how are variations priced and approved?
- Which items are long-lead, and when must we confirm them to hold the handover date?
The Six Ways at a Glance
|
Way |
Where the saving comes from |
Watch out for |
|
1. Brief and cost plan |
Fewer late changes |
Contingency spent on upgrades |
|
2. Reuse |
25% to 40% on retained elements |
Adaptation labour |
|
3. Right-sized layout |
Fewer walls and desks |
Sizing to average, not peak, days |
|
4. Design and build, early input |
Fewer fees, shorter programme |
Shifting briefs, complex buildings |
|
5. Targeted spend and efficiency |
LED payback, lower running costs |
Cutting safety or data |
|
6. Programme and lease |
Avoided delay, lower dilapidations |
Late landlord consent |
Why GXI
When comparing fit out companies in Stevenage, check that the contractor can handle design, build, compliance and handover under one team. GXI is a London based commercial office fit out and refurbishment contractor covering Cat A and Cat B fit out, turnkey design and build, office refurbishment and dilapidations across London and the Home Counties.
Our approach follows the six levers above: cost planning at concept stage, honest advice on what to retain, and a single accountable team through delivery. You can review one of our completed schemes in the Vanilla Bazaar project, read client feedback on Trustpilot and see the full scope on our Stevenage office fit out service page.