Written by the GXI team | Last updated: 23 November 2026 | Reviewed by: GXI Project Delivery
TL;DR
- Typical programme: 3 to 9 months from first survey to handover, with 4 to 12 weeks on site for a standard project and up to 28 weeks where services are replaced.
- Eight steps: brief, survey, design, approvals, procurement, strip out, build and commissioning, snagging and handover.
- Biggest delay risks: the landlord's licence for alterations (2 to 12+ weeks), bespoke joinery and furniture (8 to 16 weeks) and late design changes.
- Budget rule: hold 10% to 15% contingency, rising to 15% to 25% for older buildings.
- Stanmore factor: most space is multi-let or above shops, so landlord consent, access rules and out-of-hours working shape the programme as much as the build.
If you run a practice, agency or professional services firm out of HA7, an office refurbishment in Stanmore is rarely a single event. It is a chain of surveys, decisions, approvals and deliveries, and the projects that run smoothly are the ones where that chain is mapped before anyone orders a ceiling tile. This guide walks through the whole process in eight steps, with realistic timescales, indicative costs, the approvals you are likely to need and the local factors that affect buildings around Stanmore Broadway, Church Road and Honeypot Lane.
What Does an Office Refurbishment Involve?
Quick answer: an office refurbishment upgrades an existing workspace, usually without changing the building's structure or use. It covers layouts, finishes, lighting, services and furniture. A fit out builds a space to a tenant's requirements, typically moving from Category A (the landlord's base build) to Category B (the tenant's working environment). Most Stanmore projects blend both.
Refurbishing in place is increasingly the default choice. Recent market research points the same way:
- 37% of major occupier transactions in the first half of 2026 were stay-in-place renewals, against 49% relocations.
- Lease re-gears made up 39% of London office transactions, where tenants renegotiate to stay and upgrade.
- Refurbishments account for 47% of the under-construction pipeline in Central London.
- A refurbishment can also cut running costs. Standard efficiency measures typically reduce energy costs by 20% to 40%, and LED lighting alone can cut lighting electricity use by 85% to 90%.

Stanmore: What the Local Building Stock Means for Your Project
Stanmore sits at the end of the Jubilee line in the London Borough of Harrow, and its office market is small and fragmented rather than made up of large business parks. Space is found in serviced centres such as Stanmore Business and Innovation Centre and Devonshire House on Honeypot Lane, in traditional suites such as Stanmore Towers on Church Road, in offices above shops along Stanmore Broadway and Stanmore Hill, and in trade units around Parr Road. Harrow Council publishes a business premises directory listing available space, with asking rents ranging from roughly £10 to £40 per sq ft depending on age and quality.
That mix shapes every office fit out in Stanmore in four ways:
- Multi-let buildings: managing agents control lift bookings, delivery windows, noisy-works hours and riser access, so your contractor needs to agree to these before mobilising.
- Older stock: buildings constructed before 2000 need an asbestos survey before strip out begins, and older mechanical and electrical services often need replacing rather than refreshing.
- Landlord consent: most leases require a licence for alterations, even for non-structural partitioning.
- Occupied working: in small suites there is rarely spare space to decant staff, so phasing and out-of-hours work matter early.
For professional practices such as accountants, solicitors and clinics, acoustic privacy, confidentiality and reception presentation usually feature in the brief as well.

The Eight Steps of an Office Refurbishment
Quick answer: a typical refurbishment runs through eight steps, and several overlap. Design, approvals and procurement often run in parallel, which is how a 3 to 9 month programme stays achievable.
- Agree the brief and budget
- Survey and feasibility
- Design and specification
- Secure approvals
- Procure and order long lead items
- Strip out and prepare the site
- Build, install and commission
- Snag, hand over and review
Step 1: Agree the Brief and Budget (1 to 2 weeks)
Start with the business reasons: headcount, hybrid working patterns, client-facing areas, lease events and brand. Then set a budget that separates construction from furniture, IT and AV, professional fees and VAT, because contractor quotes often exclude them. Name one person on your side with authority to sign off decisions. Slow client sign-off is among the most common causes of programme delay.
Step 2: Survey and Feasibility
A measured survey, a services check and, for pre-2000 buildings, an asbestos survey come first. Ask the landlord for building rules, as-built drawings and the fire strategy. The findings decide whether you are doing a light refresh or a deeper services replacement, which moves cost and programme far more than any finish choice.

Step 3: Design and Specification (2 to 12 weeks)
Concept layouts come first, then technical drawings, lighting, finishes and furniture. Straightforward spaces with a clear brief finish design in 3 to 4 weeks, while complex projects with several decision-makers can take up to 3 months. Fix the design before you start on site. Mid-project changes are among the most frequently cited causes of delay and extra cost.
Step 4: Secure Approvals (4 to 12 weeks, Overlapping With Design)
Four approvals are worth checking at this stage:
- Licence for alterations: a straightforward licence typically takes around 4 weeks, while HVAC, structural or mezzanine works can take several weeks to a few months. Submit drawings, scope, specification and risk assessments together. Under a qualified covenant, a landlord generally cannot unreasonably withhold or delay consent to genuine improvements under the Landlord and Tenant Act 1927.
- Planning permission: usually not needed for internal work. It is typically required for external alterations, mezzanine floors, a change of use, or work to a listed building or in a conservation area. Harrow Council is the local planning authority, and the Planning Portal explains the process.
- Building Regulations: often required where work affects fire escape routes, emergency lighting, ventilation, electrical installations or accessibility. See GOV.UK guidance on Building Regulations approval.
- CDM 2015: the regulations apply to all construction work. The client must appoint a principal designer and principal contractor where more than one contractor is involved, and must notify the HSE if work lasts longer than 30 working days with more than 20 workers on site at once, or exceeds 500 person-days.
Step 5: Procure and Order Long Lead Items
Appoint your contractor, agree terms and place orders as soon as the design is signed off, not when the contractor starts on site. Lead times are where programmes slip:
- Stock furniture: 4 to 6 weeks. Imported or bespoke furniture: 12 to 16 weeks.
- Stock joinery: 2 to 4 weeks. Bespoke joinery: 8 to 16 weeks.
- Specialist ceilings: 6 to 12 weeks. HVAC plant, switchgear and specialist glazing: 12 to 20 weeks or more.
Step 6: Strip Out and Prepare the Site
Strip out removes old partitions, redundant cabling, floor coverings and outdated services. Dust screens, floor protection and hoarding isolate the work area. If staff remain in the building, the floor plate is usually split into zones, noisy or dusty tasks move to evenings and weekends, and escape routes, alarms and emergency lighting are kept working throughout. Under the Regulatory Reform (Fire Safety) Order 2005, fire risk assessments and hot works controls remain essential during the works. Occupied projects usually take longer and cost more than vacant ones, but avoid the expense of a full relocation.

Step 7: Build, Install and Commission (4 to 28 weeks)
New partitions, ceilings, mechanical and electrical works, flooring and decoration are followed by furniture, IT and AV. On-site time typically runs from 4 to 12 weeks for a standard project, extending to as much as 28 weeks where full services are replaced. Commissioning covers Wi-Fi, meeting room AV, access control, emergency lighting and fire detection, with building control sign-off where required.
Step 8: Snag, Hand Over and Review (1 to 2 weeks)
A snagging walk records minor defects for rectification before handover. You should receive operation and maintenance manuals and the health and safety file. If heating, ventilation or lighting changed, check whether an updated EPC is needed. Then review how the space performs a few months after move-in.
Refurbish or Relocate? A Quick Decision Test
Relocating means a new fit out, legal fees, IT and telecoms moves and dilapidations on the premises you leave, so the full cost is usually higher than the headline rent difference suggests. Staying and refurbishing tends to make sense when most of the following apply:
- Your location suits staff, clients and transport links, including the Jubilee line.
- The lease has enough term left to justify the spend, or you can negotiate a longer term or rent-free period in return for improvements.
- The building's structure and services can support your plans.
- You can phase work around the business, or decant staff for a short period.
- A move would trigger a larger dilapidation liability than the refurbishment itself.
If three or more apply, ask your contractor to price a refurbishment alongside the cost of moving before you commit either way.
How Long Does the Whole Programme Take?
Quick answer: most projects take 3 to 9 months from first survey to handover, with on-site time depending on size and scope. The figures below come from a UK fit out timeline guide.
|
Project size |
On-site time |
Full programme (brief to handover) |
|
Light refresh, under 2,000 sq ft |
2 to 6 weeks |
8 to 14 weeks |
|
Standard refurbishment, 2,000 to 5,000 sq ft |
6 to 10 weeks |
16 to 24 weeks |
|
Mid-size, 5,000 to 15,000 sq ft |
8 to 14 weeks |
20 to 34 weeks |
|
Large or multi-floor, 15,000+ sq ft |
14 to 26+ weeks |
30 weeks to 12 months |
Suites of roughly 500 to 1,469 sq ft are advertised at Stanmore Towers, so many local projects sit in the first two rows. Whether you call the scheme a refresh or a full commercial fit out in Stanmore, the same rule applies: the on-site phase is often the shortest part, and the weeks before it, covering design, licence and lead times, are where most programmes are won or lost.

What Does an Office Refurbishment Cost?
Quick answer: costs depend on scope more than size. Across the UK, light refreshes run from about £20 to £60 per sq ft and medium refurbishments from £60 to £95, while a standard Category B fit out typically costs £120 to £200 per sq ft. Outer London rates are generally 10% to 30% below central London.
|
Scope |
Typical cost per sq ft (London benchmark) |
|
Cosmetic or light refresh |
£20 to £60 |
|
Medium refurbishment (layout changes, partitions, basic services) |
£60 to £95 |
|
Standard Category B fit out |
£120 to £200 |
|
Premium specification |
£220 to £380+ |
For context, an independent UK fit out cost guide puts all-in London costs at £148 (low), £243 (mid) and £359 (high) per sq ft. As a simple illustration only, a 2,000 sq ft medium refurbishment at £60 to £95 per sq ft would be £120,000 to £190,000 at central London benchmarks, or roughly £84,000 to £171,000 after a 10% to 30% outer London adjustment. Your own figure will depend on the survey.
Budget for what quotes often leave out: furniture, IT and AV, professional fees, VAT and end-of-lease dilapidations. Fees, approvals and compliance can add 15% to 20% if they are not planned from the start. Contingency should be set by project stage:
- Standard refurbishment: 10% to 15% of construction cost.
- Older buildings or structural uncertainty: 15% to 25%.
- Early feasibility, before surveys: 15% to 25%.
- Fixed-price tender after detailed surveys: 3% to 5%.
Keep contingency ring-fenced for genuine surprises, such as degraded wiring or asbestos found behind walls, not for upgrades added mid-project. For a deeper view of phasing spend, see our guide to office design budget planning.
Why Refurbishments Overrun, and How to Prevent It
Quick answer: most overruns trace back to decisions made late, not to poor workmanship. Industry reporting suggests around 70% of UK construction projects exceed their approved budgets, and between 42% and 58% miss their programme. The usual causes, in order of how often they appear:
- Design changes and scope creep after work has started.
- Slow client decisions on finishes, layouts and sign-offs.
- Long lead items ordered too late.
- Approval backlogs with landlords, building control or other regulators.
- Skilled labour shortages affecting subcontractor availability.
- Unforeseen site conditions, including asbestos and hidden services.
You can reduce each of these with a short list of habits:
- Complete surveys before pricing.
- Freeze the design before mobilising.
- Submit the landlord licence pack early and complete.
- Order long lead items at design sign-off.
- Hold contingency and a written change-control process.
Our guide to the things to consider before refurbishing an office in London covers CDM duties and MEES in more detail. In short, MEES makes it unlawful to let commercial property rated below EPC E unless an exemption applies, with penalties of up to £150,000 for breaches, and policy proposals point towards higher minimum ratings over time.
Choosing Between Fit Out Companies: Where GXI Fits
Quick answer: choose a contractor who can take you from survey to handover under one contract and who understands multi-let buildings. When comparing fit out companies in Stanmore and the wider Harrow area, ask each one:
- Do you manage design, approvals and construction under one point of contact?
- Can you support the licence for alterations submission and landlord liaison?
- Will you act as principal designer or principal contractor under CDM 2015?
- How do you phase work when staff stay in the building?
- Can I speak to a client with a similar project?
GXI delivers turnkey office refurbishment and fit out projects, covering design, approvals, build and handover, so the chain described in this guide has a single owner. Our office refurbishment and fit out service explains the approach, and the Prideview Properties case study shows a completed project. For a realistic timeline in your building, our guide to office refurbishment duration in London is a good next read.

Your Pre-Start Checklist
Before you request tenders, gather the following. Each item shortens the programme or reduces the risk of a variation later:
- A written brief with headcount, desk ratios and room requirements.
- A ring-fenced budget that separates construction, furniture, IT and AV, fees and VAT.
- A copy of your lease, with the alterations and reinstatement clauses marked.
- The landlord's building rules, as-built drawings and fire strategy.
- An asbestos register or refurbishment survey for any pre-2000 building.
- A named decision-maker on your side, with sign-off authority.
- A realistic target date, with allowance for the licence and long lead items.
- A plan for how staff will work during the project.